Dear all,

I understand that Infinite capacity allow unlimited capacity reserved. However, how it is applied in Master scheduling?

For example, I have resource A with capacity 8hours/day. This resource is assigned to route for producing product P with 1 hour processing/1 pcs. Then I have a sales order need 30 pcs of P on 12/Aug/2015. Beside that, I also have scheduled Production order (2 pcs) which reserved 2 hours capacity on 12/Aug/2015.

Then I run Master scheduling with Infinite capacity option. The capacity reservation is: 

13/08/2015 8hrs

14/08/2015 8hrs

17/08/2015 8hrs

18/08/2015 4hrs

Why system do not reserved 6 hours or 28 hours on 12/08/2015 (currently only 2 hours are reserved on this day)? With Infinite option I expect system can reserved more than 8 hours on 12/08/2015.

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Weaveriski Profile Picture
    23,616 Moderator on at
    RE: Infinite capacity in Master scheduling

    Also in Production - Periodic - Scheduling (Operation and Job) under the default values is finite set?

  • Weaveriski Profile Picture
    23,616 Moderator on at
    RE: Infinite capacity in Master scheduling

    How are you resources in the route configured? Finite ticked?

  • Community Member Profile Picture
    on at
    RE: Infinite capacity in Master scheduling

    8_2D00_12_2D00_2015-10_2D00_30_2D00_00-PM.png

    8_2D00_12_2D00_2015-10_2D00_30_2D00_00-PM.png

  • Weaveriski Profile Picture
    23,616 Moderator on at
    RE: Infinite capacity in Master scheduling

    You will have to post the image again I am afraid, it is not showing.

  • Community Member Profile Picture
    on at
    RE: Infinite capacity in Master scheduling

    Dear Steven,

    Thanks for your answer, I set infinite in Master Plan

    This is ressult:

  • Weaveriski Profile Picture
    23,616 Moderator on at
    RE: Infinite capacity in Master scheduling

    Where exactly have you defined the infinite setting?

    The 30 pcs of Product P takes 30 hours, but if it starts on the 12/Aug it should book 8 hours, then the second production for the same day should book 2 hours, so you have 10 in an 8 hour slot.

    What infinite will not do is concatenate the time it takes 1 hour to make 1 means 30 hours which is 4 days. The other productions just add to the capacity in those days rather than rescheduling to the next free window (finite)

  • Bashir Ahmad Profile Picture
    5,248 on at
    RE: Infinite capacity in Master scheduling

    look into the master plans hope will get the answer:

    technet.microsoft.com/.../Aa591284.aspx

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Andrés Arias – Community Spotlight

We are honored to recognize Andrés Arias as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Community Member Profile Picture

Community Member 4

#2
Martin Dráb Profile Picture

Martin Dráb 2 Most Valuable Professional

#2
Guy Terry Profile Picture

Guy Terry 2 Moderator

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans