Microsoft Dynamics SL (Archived)

Negative project budgets do not properly update

(0) ShareShare
ReportReport
Posted on by

Hello,

Since upgrading from SL 2011 SP2 to SL 2015 CU1, a client is having a problem that I suspect is a bug (I have reproduced it in Demo.)

If a project has a negative budget on the Budgets tab of Project Maintenance (such as a revenue category) and they update it, the system changes it to a positive even though the minus sign (-) has been typed.

For example, if my project has -1200 and I click on this figure and then type '-1400' the result is 1400.

Is this a bug? It is driving everyone crazy and making it very difficult to enter correct budgets.  Is there a customization we can make to stop this from happening?  Please advise.  Thank you.

Laura

*This post is locked for comments

I have the same question (0)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics SL (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans