scarp planning in manufacturing module.

(0) ShareShare
ReportReport
Posted on by 155

I use Microsoft dynamics NAV 2009 R2.

I use order planning window to plan production orders.

Scenario:- I create production order for 10 PCS. After production 6 PCS was good & 4 were scarp. I recorded that production & scarp using output journal. Now i want to plan that 4PCS automatically in NAV. will it be happen.

NAV plan automatically rejects(Scarp) ?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Nareshwar Raju Vaneshwar Profile Picture
    5,596 on at

    Hi Sampath,

    You can define Scrap % in Item and BOM.

    Check the link: www.olofsimren.com/scrap-in-production

    Hope it helps.

  • Suggested answer
    Alexander Ermakov Profile Picture
    28,096 on at

    As Nareshwar mentioned, you can add scrap % info to the item card:

    msdn.microsoft.com/.../hh168174(v=nav.90).aspx

    You can also post scrap manually in the output journal:

    msdn.microsoft.com/.../hh173247(v=nav.90).aspx

    You can also define fixed scrap or %% for production routing.

  • Sampath Profile Picture
    155 on at

    Thanks, for valuable idea. I use those features as well.

    But the problem is following scenario.

    Assume i have sales order for 10 PCS. I create release production order against that demand.

    then i produce 10PCS but 7 was good & 3 were damaged. I recorded that result in output journal (7 good, 3 scarp)& post . Now i want to know how system suggest to plan that 3 pcs   in planning tool (order planning or planning worksheet). ?

  • Sampath Profile Picture
    155 on at

    Thanks Nareshwar, for valuable idea. I use those features as well.

    But the problem is following scenario.

    Assume i have sales order for 10 PCS. I create release production order against that demand.

    then i produce 10PCS but 7 was good & 3 were damaged. I recorded that result in output journal (7 good, 3 scarp)& post . Now i want to know how system suggest to plan that 3 pcs   in planning tool (order planning or planning worksheet). ?

  • Suggested answer
    Community Member Profile Picture
    on at

    Actually in NAV, when you post the Scrap, system would still have pending Order Quantity in "Remaining Quantity" field and hence system would not suggest you any further quantity via planning engine.

    System is only recording Scrap Quantity in Capacity Ledger Entry and would not have any quantitative effect on production order.

    What you can do here is, just create the Scrap Quantity as flow field in Production Order, so that user would be able to know the Production Order Quantity, Actual Output Quantity & Scrap Quantity. This way, user would understand the pending production order quantity and can manually book the output and related consumption in the system.

    OR,

    User can Finish the existing production order and create the new production order manually as per the Scrap Quantity.

    Hope this helps.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans