Subcontracting : How can we use purchase lead time instead of route calculated time?

(1) ShareShare
ReportReport
Posted on by 31
Hi dear community, 
 
In a context of subcontracted work where  I don't need to schedule the operation internally. 
I need to have the following scenario : once I estimate the Production order, Subcontracting purchase order is created automatically and make sure that receipt date of the PO follow the item lead time regardless of the ordered quantity. 
I'm currently facing the following issue: once I release the production order, the receipt date = end date of the production order which is not the required behavior.
 
Thanks for your help. 
 
best regards 
OA
  • Rolly R Profile Picture
    Rolly R 6 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    Hi Omario
     
    Did you get this to work? I have the same situation.
    I tried the suggestions from the other users but it still does not work.
    I created a purchase price agreement on the service item with a lead-time of 14 days, combined with a queue before = 7 days (168 hours) on my vendor route operation. This is to see which one the system will use.
    The production order is created manually and scheduled manually. The system still uses the queue before time in the planning.
    However, the requested receipt date of the purchase order line for the service item is actually at the end of the queue before time. I guess I need to setup the queue before time to match the lead-time on the trade agreement? The system seems to discard the lead-time on the service item.
  • Suggested answer
    lvdtang Profile Picture
    lvdtang 1,913 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    Hello OA,
     
    Have you already tried to setup a purchase trade agreement? In purchase trade agreement you can add the supplier, item and leadtime. 
     
     
    Make also sure that you activate the paramer 'Find trade agreements' of the Master Planning parameters.
     
     
    Best regards,
     
    Laurens van der Tang
  • Suggested answer
    ColbyGallagher Profile Picture
    ColbyGallagher 3,666 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    How are you creating your production order?  It sounds like your coverage group for the service item is either manual (and thus PO only creates during estimation of the production order and not during master planning) or you are manually creating the production order, then estimating.  If you instead let the planning engine create your production orders and your directly derived subcontract PO's, you'll get a PO that respects lead time of the service item.  
  • Omario Profile Picture
    Omario 31 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    HI, 
     
    Its a Route with a unique subcontracted operation. 
    And yes Route and resource type and BOM line type are set to vendor.
    I want to make sure that delivery date on the subcontracted purchase order take into account lead time of the purchased item (default order setting)  regardless of the route times and  produced quantity. 
    Thanks in advance. 
  • CU31050813-0 Profile Picture
    CU31050813-0 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    HI, 
     
    Its a Route with a unique subcontracted operation. 
    And yes Route and resource type and BOM line type are set to vendor.
    I want to make sure that delivery date on the subcontracted purchase order take into account lead time of the purchased item (default order setting)  regardless of the route times and  produced quantity. 
    Thanks in advance. 
  • andreasraithel Profile Picture
    andreasraithel 4,834 Super User 2024 Season 2 on at
    Subcontracting : How can we use purchase lead time instead of route calculated time?
    Hy,
    I assume you have the "route type" set to Vendor and added the item to purchase.
    How the Oper No set? Are there any operations after that ext. Vendor work?
    Pls share more details.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Congratulations 2024 Spotlight Honorees

Kudos to all of our 2024 community stars! 🎉

Meet the Top 10 leaders for December

Congratulations to our December super stars! 🥳

Start Your Super User Journey

Join the ranks of our community heros! 🦹

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,735 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,466 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans