Hi I am creating rework batch order. When I check My estimation cost, always Rework FG cost display as 1. But When run RAF, consumption cost taken as correctly. Any setting did I miss to display the Estimation cost wrongly.?

  • ToddB Profile Picture
    on at
    RE: Rework Batch Order

    Hi Neranjan,

    In checking on this, I found this may be the nature of a rework batch as it is to re-do a production order that didn't finish or was defective the first time.

    The rework batch is created with just one formula (BOM) line for the finished good item so that might explain why it is showing as 1.  

    It is not like a regular production order with all the individual materials listed.

    Create a rework batch order

    docs.microsoft.com/.../create-a-rework-batch-order

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge 🌸

WIN Power Platform Community Conference 2025 tickets!

Jonas ”Jones” Melgaard – Community Spotlight

We are honored to recognize Jonas "Jones" Melgaard as our April 2025…

Kudos to the March Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 294,095 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 232,866 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,158 Moderator

Leaderboard

Product updates

Dynamics 365 release plans