Hi there,
In our dynamics environment, it seems Estimated Fees are calculated wrong.
Basically, whenever we create a task and assign a resource to that task, estimated fees get updated to show the total of the last resource not the total of all the task lines.
I did a bit of investigation and it seems like the column "remaining labor sales" in the Project table is the one not updating correctly.
I'm not sure if this is due to some flow/process which is switched off, but I can't really see anything.
For example:
If I have task X for resource A charging 100 a day for 10 days, my estimated fees show as 1000.
Then if I add task Y for resource B charging 200 a day for another 10 days, the estimated fees for the project get updated to 2000, not 3000.
any idea on how to fix this?