How can I include hours using Flexible Column Maintenance

(0) ShareShare
ReportReport
Posted on by 50

Attempting to get project task summary report to provide MTD, YTD and PTD (project to date) hours.  How can we get this?

 

*This post is locked for comments

I have the same question (0)
  • Jana Glaser-MacDonald Profile Picture
    on at

     

    Dear Adam,

    MTD = Current units , this is column 1
    PTD = Project to date Units , this is column 3
    PTD is YTD if a project is NOT balance foward at year end.

    For budget in units:
    1. Open Report in Crystal reports
    2. In the field explorer pane Click on Field = Column5
    3 Right click and select edit
    4. Change {pjptdsum.eac_amount} to pjptdsum.eac_units}
    5. Repeate proceduer for Column5
    6. Change {pjptdsum.total_budget_amount} to {pjptdsum.total_budget_units}

    The ETC columns will need to be changed so varience can compute on units rather than amounts.

    ETC,
    {@Column5} - {@Column3}

    gf1etc, gf2etc

    {@Gf1column5} - Sum ({@Column3}, {pjptdsum.project})

    I hope this is what you are thinking regarding hours/units on pa100

    Best Regards,

    Jana

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics SL (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans