Question for everyone here for implementation go live.
We were originally planning on importing orders in progress into BC from our old ERP. Currently we are sitting at approx 1000 WIP orders + purchase orders (every one of our orders is special order so has 1 or more POs). These orders on the floor have IDs from the old ERP and there is concern details might be lost in transition.
We are thinking to put new orders into BC at go-live and finish as much as we can in the old ERP right up until contract expiry (approx 2 weeks) then work to transition those over into BC which should be a much smaller number.
Finance is concerned about this approach as numbers would be misaligned. What best practices are you aware of to make this parallel system work keeping our numbers aligned?