Hello,
When adding holidays to a calendar the holidays still have working times according to what's set up as default. Is it possible to make resource scheduling respect holidays or do I have to manually remove the working times on dates that have a status as holiday?
Br Joachim
Hi Joachimpwc
Unfortunately, there is no relationship of holiday in HR module and calendar linked to resource PMA.
If you need this to update, you have to either need to do some customization or manually update the calendar of each resource.
Please let us know if this helps.
Thanks,
Hi Joachim,
Maybe you should customize to meet your requirement.
And you can view the links below briefly.
Set up a holiday schedule (Dynamics 365 Customer Service) | Microsoft Learn
Incorporate Holiday schedules in calendars in Dynamics 365 CRM - Microsoft Dynamics CRM Forum Community Forum
Best Regards,
Hana
This post is my own opinion and does not necessarily reflect the opinion or view of my company.
Please mark as verified if the answer is helpful. Welcome to join hot discussions in Dynamics 365 Forums.
Hello Gaurangkumar Jani and Hana,
Thank you for your replies and assistance. You answered my question.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
Thanks to all of our 2025 Community Spotlight stars!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
André Arnaud de Cal... 555 Super User 2026 Season 1
Giorgio Bonacorsi 364
Diego Mancassola 259