Microsoft Dynamics AX (Archived)

Capacity Reservations - System do not select different resources (based on capability)

(0) ShareShare
ReportReport
Posted on by

Hi All,

I have one finished good that requires a specific resource capability. This specific capability has assigned 2 different resources. I have 2 different sales orders with requested receipt date is in 6 days. The capacity is not enough to be produced during deadline by one resource (machine).

However when I run Master Schedule instead of using both resources system choose only one resource. As a result the planned end date is 3 weeks later (out of deadline). 

How the system can allocate load to both resources?

@ job scheduling, finite capacity

BR,

Michalis

*This post is locked for comments

I have the same question (0)
  • Weaveriski Profile Picture
    23,618 Moderator on at

    I would just like to clear up the question slightly.

    In the route you are telling AX to use how many resources?

    The supply of the two SO's is by two works orders or one?

    Your finite capacity was not working in a previous post, but this would suggest it is working and adding the second SO to the first?

    Can you post some screen shots and a walk through of your issue please, it is not clear the way it is asked here I am afraid.

  • Community Member Profile Picture
    on at

    HI Steaven,

    my replies:

    In the route you are telling AX to use how many resources?  Correct

    The supply of the two SO's is by two works orders or one? Two

    Please see the print screens (item Nr 9001, Op. No=20)

    Rea

  • Weaveriski Profile Picture
    23,618 Moderator on at

    Hi Michalis

    There are not print screens attached to the reply I am afraid.

  • Community Member Profile Picture
    on at

    HI Steaven,

    my replies:

    In the route you are telling AX to use how many resources?  Correct

    The supply of the two SO's is by two works orders or one? Two

    Please see the print screens (item Nr 9001, Op. No=20)

    8231.finite6.png

    Resource Requirements

    6165.finite4.png

    Applicable Resources

    1778.finite5.png

    Master Schedule runs without warnings (!)

    8231.finite6.png

    Please notice that ProdOrder end date is different from SO Requirement Date and there was no warning (the same happens to the 2nd SO)

    2845.finite7.png

    All capacity reservations are in the 1st resource MHX 70 (for both two planned orders). There are no reservations on MHX 80 although dates are not met.

    finite8.png

    Finally these are the Master Plan Parameters

    finite9.png

    Thanks,

    Michalis

  • Community Member Profile Picture
    on at

    Hi Steaven,

    can you see them?

  • Weaveriski Profile Picture
    23,618 Moderator on at

    I can see them now. So are MHX70 and MHX80 finite? Have you set finite in the periodic job scheduling default values? Can you show the netrequirements, can you show the scheduling and the choosing of one resource? What is the capacity of the unused resource? There is, unfortunately, an awful lot of setup here.

  • Weaveriski Profile Picture
    23,618 Moderator on at

    With regards to your no warning this would come from the action and future messages in planning - so you need to configure those and react to them.

  • Community Member Profile Picture
    on at

    Yes they are finite.

    Net Requirements:

    finite11.png

    Production Control->Periodic->Scheduling->Job Scheduling I think is a next step after Master Planning. The question is why Master Planning do not use alternative resources.

    Alternative Capacity (MHX 80) is 8 hours per day

    finite11.png

    Thanks a lot for your effort!

  • Community Member Profile Picture
    on at

    Any direction where to look in order to configure?

  • Weaveriski Profile Picture
    23,618 Moderator on at

    Well you need to start analysing your MRP and deciding if the issue is capacity or material - so look at the future and action messages, and look at your configuration of the coverage groups. Master Planning schedules, the job scheduling part is indeed when you reschedule it, but fundamentally MRP schedules it to drive material and capacity, it looks at the settings.

    There are future and action messages, are the orders being moved out.

    I am not sure what you mean by "Any direction where to look in order to configure". First you need to understand why it is doing what it is doing, it is pushing elements out, the question is why, so look at the pegging, look at the scheduling and then start to look at the configuration of the item coverage etc.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans