Hi All,
I have one finished good that requires a specific resource capability. This specific capability has assigned 2 different resources. I have 2 different sales orders with requested receipt date is in 6 days. The capacity is not enough to be produced during deadline by one resource (machine).
However when I run Master Schedule instead of using both resources system choose only one resource. As a result the planned end date is 3 weeks later (out of deadline).
How the system can allocate load to both resources?
@ job scheduling, finite capacity
BR,
Michalis