Hi all, 

Recently I have created and tested in a Sandbox environment. Now we are ready to move other to the production environment that has been setup. Is there an easy was to export the setup of the current system, or do I need to re-create everything from scratch again?

Kind regards,

Matt

I have the same question (0)
  • Suggested answer
    Parag Chapre Profile Picture
    12,254 Most Valuable Professional on at

    Hi Matthew,

    If you want a specific setup then you can just use DMF. Export your data from TEST and import it to PROD.

    If you want all data then you can copy the database from TEST to PROD but you need to change some configuration in PROD.

  • Matthew Falle Profile Picture
    90 on at

    Hi Parag,

    Thanks for the quick response.

    I would want to keep all data that is currently in the system other than any Leave Requests. Do you know how I would accomplish this?

    Should I just copy the environment in Lifecycle Services and then delete the Leave Requests from the tables?

    When copying do you know if this will also copy and extra custom fields, Power Automate workflows, Virtual Entity setup or PowerApps?

    Kind regards,

    Matt

  • Matthew Falle Profile Picture
    90 on at

    I see that I can't copy a sandbox environment to production in life cycle services, do you know a way around this?

  • Suggested answer
    Parag Chapre Profile Picture
    12,254 Most Valuable Professional on at

    If you don't see any option then one of the possible solutions is DMF. You can also raise a support request with Microsoft.

  • André Arnaud de Calavon Profile Picture
    305,196 Super User 2026 Season 1 on at

    Hi Matthew,

    There is only a way to copy the database from PROD to UAT. It is all written in the documentation where it is stated to use the production instance as golden configuration environment and copy the database for testing to UAT. If you made changes in UAT, then you can copy them using data entities or re-apply them manually in the production instance.

    Prepare for Human Resources go-live - Human Resources | Dynamics 365 | Microsoft Docs

    Copy an instance - Human Resources | Dynamics 365 | Microsoft Docs

  • Matthew Falle Profile Picture
    90 on at

    Hi Andre,

    I have manged to copy the customisation by downgrading prod to a sandbox environment, copying uat to it, then changing it back to prod.

    Does anyone know what would be the easiest way to export and import workers, leave plans, users etc?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 692

#2
André Arnaud de Calavon Profile Picture