Planning Optimization: Master scheduling planned order number sequence format?

Posted on by 35

Hello,

I have started exploring the planning optimization in D365 F&O (version 10.0.16) on our Preprod environment. After we turn-on planning optimization and run master planning, one thing I noticed is that the number sequencing of the planned order (Master Planning -> Planned Orders) is different as compare to when I turn-off planning optimization (i.e. previous version: master planning). It seems that planning optimization is not picking up the number sequencing for planned orders, although it is already configured under (Setup -> Master planning parameters > Number Sequences -> "Master Scheduling planned order number"). FYI, it is correctly picking up this number sequence format when I turn-off planning optimization, and use the previous master planning.

Example below:
Planning Optimization: Turn-On: Planned Order Number generated is 0009000001 (Master Planning -> Planned Orders). Issue: Not picking up number sequencing format, although it is correctly configured in the setup.

Planning Optimization: Turn-Off (means its back to the previous Master planning): Planned Order number generated is MPO-126218. Correctly picking up number sequencing from the master planning parameters.

Please find below the two planned order numbers snapshot.

Question: Any idea from where I can find and set this number sequence format for planned order when we turn-on planning optimization?

Hopefully, Microsoft has not hardcoded this inside the system because planning optimization is new :).

Thanks,
Ahsan

pastedimage1615425447018v1.png

  • Microsoft Profile Picture
    Microsoft on at
    RE: Planning Optimization: Master scheduling planned order number sequence format?

    planning service has no parameters to be set and it might be hard coded,

  • Verified answer
    André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 290,263 Super User 2024 Season 2 on at
    RE: Planning Optimization: Master scheduling planned order number sequence format?

    Hi Ahsan,

    I haven't got the opportunity to look at the planning service as it runs on tier2 and higher tiers only.

    It wouldn't surprise me if the planning service is using their own number sequence which might be indeed hard coded. The planning service is a microservice which is running outside Dynamics 365. It is designed that all calculations will be done in memory to get the highest possible performance. Taking the number sequence settings into account, it could potentially have a drawback  on the performance.

  • ahakhanAAK Profile Picture
    ahakhanAAK 35 on at
    RE: Planning Optimization: Master scheduling planned order number sequence format?

    Hi Jasmine, its on cloud. No, I couldn't find any feature to enable this.

  • Microsoft Profile Picture
    Microsoft on at
    RE: Planning Optimization: Master scheduling planned order number sequence format?

    Hi Ahsan, thanks for the detailed information for this issue.

    May I know if your environment is dynamics 365 on cloud or on premise environment?

    could you check if there any related feature need to be enabled?

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 9th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,263 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 228,112 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans