Hello All ,
Dynamics has a provision that items can be produced using a costing sheet or without a costing sheet,but i'm curious to understand where/how to get the cost of the material if no costing sheet is created.
Does anyone has experience on this ?
Hi,
Is your issue solved?
hi,
You can always get from multiple ways , if you want to review inventory cost at any point in time you can go to inventory transactions or inventory value report
also COGS main account alwaays give the consumption details depending on valuation method
Hi lally,
If you want to view the production cost of the produced item, both the estimated cost and realized cost can be found from Production control > Production orders > All production orders > Manage costs > View calculation details.
Select “Overview costing”.