How Business Central calculate the unit cost in assembly orders

(0) ShareShare
ReportReport
Posted on by 101

Hello,

Checking the following assembly order, we want to know how business central calculates de unit cost because we don´t know how to get that value in this example.

pastedimage1658501593407v3.png

I appreciate any help you can provide.

  • Suggested answer
    YUN ZHU Profile Picture
    85,819 Super User 2025 Season 1 on at
    RE: How Business Central calculate the unit cost in assembly orders

    Hi, Can you see the problem on the page below?

    pastedimage1658706273781v3.png

    pastedimage1658706282196v4.png

    Hope this helps.

    Thanks.

    ZHU

  • Suggested answer
    Dallefeld Profile Picture
    175 User Group Leader on at
    RE: How Business Central calculate the unit cost in assembly orders

    How many were you producing on the assembly order?

    Agree with NorthW , run adjust cost and see if your costs are adjusted.

  • Suggested answer
    Inge M. Bruvik Profile Picture
    1,029 Moderator on at
    RE: How Business Central calculate the unit cost in assembly orders

    Have you checked the cost value that the item ledger entry shows for the finished assembled product?

    And can you show a screenshot of that?

    The average cost on the item card looks no where near the cost shown in the assembly order.

    Maybe cost adjustment have been processed after the assembly order was posted?

  • Alejandro Bohorquez Profile Picture
    101 on at
    RE: How Business Central calculate the unit cost in assembly orders

    Hello, thanks for the help, here is the screenshot that you request:

    1. Item Card

    pastedimage1658507517563v1.png

    2  Assembly BOM

    pastedimage1658507613218v4.png

  • Suggested answer
    Dallefeld Profile Picture
    175 User Group Leader on at
    RE: How Business Central calculate the unit cost in assembly orders

    1. Can you provide a screen shot of the item card for AC-040?

    2. Can you provide a screen shot of the assembly BOM for the item that you are assemling?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Ramesh Kumar – Community Spotlight

We are honored to recognize Ramesh Kumar as our July 2025 Community…

Congratulations to the June Top 10 Community Leaders!

These are the community rock stars!

Announcing the Engage with the Community forum!

This forum is your space to connect, share, and grow!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
Sohail Ahmed Profile Picture

Sohail Ahmed 2,655

#2
Mansi Soni Profile Picture

Mansi Soni 1,574

#3
YUN ZHU Profile Picture

YUN ZHU 1,453 Super User 2025 Season 1

Featured topics

Product updates

Dynamics 365 release plans