How Business Central calculate the unit cost in assembly orders

(0) ShareShare
ReportReport
Posted on by 101

Hello,

Checking the following assembly order, we want to know how business central calculates de unit cost because we don´t know how to get that value in this example.

pastedimage1658501593407v3.png

I appreciate any help you can provide.

I have the same question (0)
  • Suggested answer
    YUN ZHU Profile Picture
    89,835 Super User 2025 Season 2 on at
    RE: How Business Central calculate the unit cost in assembly orders

    Hi, Can you see the problem on the page below?

    pastedimage1658706273781v3.png

    pastedimage1658706282196v4.png

    Hope this helps.

    Thanks.

    ZHU

  • Suggested answer
    Dallefeld Profile Picture
    193 User Group Leader on at
    RE: How Business Central calculate the unit cost in assembly orders

    How many were you producing on the assembly order?

    Agree with NorthW , run adjust cost and see if your costs are adjusted.

  • Suggested answer
    Inge M. Bruvik Profile Picture
    1,035 Moderator on at
    RE: How Business Central calculate the unit cost in assembly orders

    Have you checked the cost value that the item ledger entry shows for the finished assembled product?

    And can you show a screenshot of that?

    The average cost on the item card looks no where near the cost shown in the assembly order.

    Maybe cost adjustment have been processed after the assembly order was posted?

  • Alejandro Bohorquez Profile Picture
    101 on at
    RE: How Business Central calculate the unit cost in assembly orders

    Hello, thanks for the help, here is the screenshot that you request:

    1. Item Card

    pastedimage1658507517563v1.png

    2  Assembly BOM

    pastedimage1658507613218v4.png

  • Suggested answer
    Dallefeld Profile Picture
    193 User Group Leader on at
    RE: How Business Central calculate the unit cost in assembly orders

    1. Can you provide a screen shot of the item card for AC-040?

    2. Can you provide a screen shot of the assembly BOM for the item that you are assemling?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Mansi Soni – Community Spotlight

We are honored to recognize Mansi Soni as our August 2025 Community…

Congratulations to the July Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
Sohail Ahmed Profile Picture

Sohail Ahmed 2,899 Super User 2025 Season 2

#2
Sumit Singh Profile Picture

Sumit Singh 2,444

#3
Jeffrey Bulanadi Profile Picture

Jeffrey Bulanadi 2,304

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans