Hello Experts, thank you very much for taking the time to read my question and share your knowledge.
I am a little frustrated since I have been trying to understand for several weeks why it does not work as I have ever executed this action, below I will explain my scenario.
In January 2023, execute the following report as follows within the planning sheet
Once it finished it showed me something like this
It gives me 52 lines which belongs to our forecast that we load into the system (All lines belong to a Sunday of the month)
When I go to see the list of components of that product, it also shows me the materials correctly, but within it there is a product that is semi-finished and uses different components, which I will mark with a yellow line.
So I decided to run the report again but now with the following filters
And it generates another 52 Lines based on the 52 where it appears as a component and this really works perfectly for us.
Subtracting one day from the date where that component is needed to generate a couple of lines like this
This works for 2023
I'm trying to do practically the same thing but now I'm trying to do it with dates from January 1, 2024 to December 31, 2024
I show screens of what I do...
It shows me the lines correctly here on the correct dates...
But when I ran the report for the second time filtered to the semi-finished product (PSN001) that is in the components of the finished product with the number PSN0001, it summarizes everything in 1 line and not like when I did it for the 2023 forecast, looking more or less like this:
He summarizes everything in a single line and he no longer believes the lines for 2024, he stays until the last day of December 2023
My question is, what do I need to configure or do within the system so that the forecast comes out like when I run it with dates of 2023?
Again, I appreciate the time you took to read my post and for any kind of help I've been dealing with this for a while and I really don't know what to do...
greetings and good night