Reporting Finished Quantities on Multiple Resources for the Same Operation in PFE

(1) ShareShare
ReportReport
Posted on by 18
Hello experts,
 
I’m currently facing a scenario and would appreciate your guidance.
 
We have a route operation called Cutting, which is the final step in the production route. This operation can be performed on either Cutting 1 or Cutting 2 machines. The preferred resource is Cutting 1, but if Cutting 2 is available, it can also be used. This decision may be made even after the production order has been started (status = Started). In case Cutting 1 breaks down, Cutting 2 should be used as a fallback.
 
In practice, around 90% of the time, only Cutting 1 is used for this process.
The client needs to be able to report quantity as finished on both Cutting 1 and Cutting 2 (as far as I know, that means it can't be a secondary operation).
 
Please note:
  • The client is not using finite capacity.
  • The client does not rely on the system for automatic operation scheduling.
  • The client is using the Production Floor Execution (PFE) interface.
Has anyone dealt with a similar setup? What would be the best approach to handle this scenario in Dynamics 365 F&O?
Thank you in advance for your support.
I have the same question (0)
  • Suggested answer
    Ranjanj Profile Picture
    294 on at
    Hello
     
    If finite is not used , than you can change the resource, from route resource requirement.
  • CU22050047-0 Profile Picture
    18 on at
    Thank you for your response, Ranjanj! That helped solve the issue of changing the resource while production is already running.
     
    However, I’m still trying to figure out how to run both resources at the same time, even though my default route isn’t configured for parallel operations.
    Here’s what I’ve tried so far, by modifying the operation on the PBO route:
    • Changed the resource load quantity to 2
    • Assigned a capability to the resource requirements that includes both resources
    • Set the priority of both resources to 0
    • In the PBO’s route, the minimum level needed is also set to 0
    Despite these changes, only one resource is being used and 1 job was created at a time after scheduling jobs. Is there a way to allow both resources to run simultaneously under these conditions? Keeping in mind that we need to report quantity as finished on both resources.
     
    Any insights or suggestions would be greatly appreciated!
     
    Thanks in advance,

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 301 Super User 2025 Season 2

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 118 Super User 2025 Season 2

#3
Siv Sagar Profile Picture

Siv Sagar 105 Super User 2025 Season 2

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans