Hi,
Trust you are well.
I have the following questions regarding demand generated by subcon orders.
As I have understood, BC uses the following process:
- Looks at all released production orders with atleast 1 subcon workcenter
- Converts production order to purchase order + work order
- Purchase order contains information on inventory supply
- Work order is basically for billing as per workcenter assumptions/labor etc.
Its unclear to me whether after the released production order is converted to subcon purchase order:
1. the component demand from the original released production order will be ignored or consider active by the planning engine?
2. if the subcon purchase order has been set to planning flexibility = None, then will the planning engine suggest a new production order, or will it assume that the demand is being fulfilled by the incoming subcon purchase order