Hi Experts,
I do finite production capacity.
I face a scenario when I need to change the production quantity when the production running (started status), I can change the production quantity but the Gantt Chart is not changing as per new quantity is submitted. eg: report remainder as finished is 10,000 - Gantt Chart ends at 6.00 PM, when I add another 100 on top of what has been plan - Gantt chart still ends at 6.00 PM.
How can I reflect the changes to Gantt Chart?
If the production has not been started I can reset the status to schedule and schedule it (no issue), but when the production is already started it gives me an error when I tried to reset the status.
Please advise.
If you are still facing this issue you can open a support case through your support channels for further analysis.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,253 Super User 2024 Season 2
Martin Dráb 230,188 Most Valuable Professional
nmaenpaa 101,156