Hi,
One of our customers requires a way to block the feedback report trough AX MES terminal if the previous operation does not have feedback. For example if they have a simple route of three ops:
OP-10 "Clean"
OP-20 "Assemble"
OP-30 "Paint"
They cannot complete OP-20 if OP-10 was not completed.
There is a parameter in Manufacturing execution section that seems to be related to this, but I am not sure if only affects the RAF quantities of the entire WO.
It does not seems to be considering the Completed quantities in the operations..
Many thanks