Suggested answer

Why Is More Quantity Being Requested?

(0) ShareShare
ReportReport
Posted on by 3,494

Hi:

When I tested the entry and processing of a Released Production Order in Manufacturing, the Components window "wanted" a quantity "one more" for each of the BOM's components.

For example, one of the components of the BOM calls for a quantity of only 4.  But, the Components window wanted 5.

I did not discover this, until I processed lot numbering in Item Tracking Lines of the Components window.

No scrap percentage or anything along those lines is in place.

And, I was able to adjust the quantity manually in order to correct this.

But, why is more quantity than what is in the BOM being requested?

Thanks!

John

  • john.ellis Profile Picture
    3,494 on at
    RE: Why Is More Quantity Being Requested?

    Hi Kim: "Were you using Consumption journal or Production Journal?"

    I wasn't using the Consumption Journal. 

    I opened the Production Journal once.  But, I made no changes in that Journal. 

    And, there is Backward Flushing throughout.

    John

  • Suggested answer
    Inge M. Bruvik Profile Picture
    1,029 Moderator on at
    RE: Why Is More Quantity Being Requested?

    As you say you have no scraping defined. Can it have something to do with unit of measures. Do you have the same base unit of measure for the item that the UOM being used in your BOM ?

  • Suggested answer
    DAnny3211 Profile Picture
    9,278 Moderator on at
    RE: Why Is More Quantity Being Requested?

    hi

    look this

    learn.microsoft.com/.../receive-more-items-than-ordered

    DAniele

  • Suggested answer
    Manan_Shah Profile Picture
    1,459 on at
    RE: Why Is More Quantity Being Requested?

    Hi John,

    Possible scrap is generated, so system asking for additional components to complete the Production Order. 




    Many Thanks,
    Manan

  • Dynamics 365 Profile Picture
    2 on at
    RE: Why Is More Quantity Being Requested?

    Hello John,

    Can you please send the Screenshot of this scenario so that I will get more clearance on this and try to provide you a better Solution.

    Thanks

  • Suggested answer
    Dallefeld Profile Picture
    175 User Group Leader on at
    RE: Why Is More Quantity Being Requested?

    That is not standard unless you have scrap on items or BOMs. Were you using Consumption journal or Production Journal?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Ramesh Kumar – Community Spotlight

We are honored to recognize Ramesh Kumar as our July 2025 Community…

Congratulations to the June Top 10 Community Leaders!

These are the community rock stars!

Announcing the Engage with the Community forum!

This forum is your space to connect, share, and grow!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
Sohail Ahmed Profile Picture

Sohail Ahmed 2,655

#2
Mansi Soni Profile Picture

Mansi Soni 1,574

#3
YUN ZHU Profile Picture

YUN ZHU 1,453 Super User 2025 Season 1

Featured topics

Product updates

Dynamics 365 release plans