Yes, setup time does not change with quantity, run time does.
Thank you for your answer.
I also had the idea of using the setup time instead of the runtime, but then I can only ever map a fixed time. If I can produce 500kg in 1 hour, but produce 800kg, the machine runs theoretically 2 hours, but the setup time remains at 1 hour because it's fix.
then I probably can not avoid an customization as it looks like
I don't think it's possible with standard route consumption calculation methods as all 4 of them are quantity dependent.
The only workaround option I could think of is to use setup time instead of run time as it does not change with quantity being produced.