Is there a way to make the Start and End date different in the job planning lines? Whenever I update these in the planning lines it always defaults to the same date
The Job Task Start Date and End Date simply sum or link to the Job Planning Lines Planning Date/Planned Delivery Date. It will show the earliest Job Planning Line Date as the Start Date and the later Job Planning Line Date as the End Date.
If you only had one Job Planning Line, or multiple Job Planning Lines with the same date, then your Job Task Start and End Date will be the same. But if you have multiple Job Planning Line each with different dates then your Job Task End and Start Dates should be different.
Hi, If you only have one Job Planning Line, they are always the same. One of them takes the minimum date, and the other takes the maximum.
Start Date:
End Date:
So if there are two Job Planning Lines with different dates, they will be different.
Hope this helps.
Thanks.