Cost Adjustment from one project to another project

(0) ShareShare
ReportReport
Posted on by 4,055

Hi all

I am trying to adjust the cost from one project to another project by using "Adjust transaction" functionality but when i select my project to transfer the cost i can not see all the posted transactions and all these transactions are of item type generated from the purchase order.

The project from which i want to transfer the cost, is estimated and estimation posted, also in the parameters i checked mark the "Estimated". Some of the transaction which i found i already transferred to the other project.

Can anyone guide me how can i trace why the cost not showing, which area i have to look into even if i have to look into tables. I m using AX 2012 R2 CU7

Please advise.

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Imran,

    Can you reverse or delete the last estimate and then try to adjust the transaction?

    Ludwig

  • imran ul haq Profile Picture
    4,055 on at

    Thanks Ludwig for your reply.

    I already reverse the estimation, but no luck.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Imran,

    Did you only reverse the last estimation or all of them?

    Another thing that could work for you is doing the transfer of the costs in a GL journal. This works only if you use a split posting where you enter the different projects into single lines e.g. line 1: Project A +5$ category XYZ, line 2: Project B -5$ category XYZ.

    Hope this helps,

    Ludwig

  • imran ul haq Profile Picture
    4,055 on at

    Hi Ludwig

    Thanks for your reply.

    The project had two estimation and i reverse both of them.

    As the cost to transfer is of Item so i can not use the GL entry as only expenses can be recorded there.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Imran,

    Can you use a project item journal to do the "movement" of the transactions?

    Something like that:

    8473.proj.png

    Ludwig

  • imran ul haq Profile Picture
    4,055 on at

    Hi Ludwig,

    Item Journal I cannot use as the item is the service type.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Imran,

    How did you record the transaction on your project the first time?

    What might be another option is creating an item requirement and posting the packing slip with negative and positive quantities on your projects.

    What you should also check are the Project Parameters. In the General tab you can specify which transaction status are allowed for adjustment.

    Best regards,

    Ludwig

  • imran ul haq Profile Picture
    4,055 on at

    Hi Ludwig

    I create the PO for the service item from the item requirement.

    I am using the Fixed price Percentage completion so packing slip option i believe i cannot use.

    And in the parameter i checked mark all the option except elimination.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Can you record another PO for your service item with negative sign for the Project where you want to want to have the correction and a second PO for the Service item for the Project where you want to have the costs? This should work in my opinion to make the "adjustment".

    Ludwig

  • imran ul haq Profile Picture
    4,055 on at

    Hi Ludwig,

    Thanks for your reply and the suggestion, i did the same to transfer/adjust the cost. My problem got solved but still i am wondering why in the adjustment form posted transactions are not showing, can you please guide me what can be the reason and how i can trace.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 24

#2
Michel ROY Profile Picture

Michel ROY 14

#3
Jagadabi Profile Picture

Jagadabi 6

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans