Hello,
It is very usual in the industry that an operator runs 3 machines or more at the same time.
I was told that if you enter the machine as primary resource and the operator as the secondary resource in D365FO and assign 3 one hour work order to the operator the planning functionality of D365FO will not be able to parallelize them due to the operator constraint...
Would anyone know if there is a way to overcome that issue?
Thanks for your help,
LearningTof.