Only one production order with multiple lines when use MTO (make to order)

(0) ShareShare
ReportReport
Posted on by 500

Hi

When i use manufacturing policy in item/SKU card as MTO(Make to order) & if i plan multiple level production orders then system (NAV 2009 R2) will plan only one production order with multiple lines.

But same scenario did on NAV 2013,

It planned same thing but deference production orders.

all the parameters set as follows in both versions,

  • Manufacturing policy of item/SKU cards = MTO
  • Reorder policy of production items= Order

Any one note that situation? is it improvement in NAV 2013?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at

    In this case, system will be create only one planned PO with multiple lines. In NAV2013 is the same situation.

    "Make-to-Order: Explodes the BOM and creates an additional production order or production order proposal line for each level in the BOM structure where that item's manufacturing policy has also been defined as make-to-order. If you make multilevel production orders, then the manufacturing policy for the parent item and the component items at all levels must be make-to-order."

  • Suggested answer
    Tanya Susan Profile Picture
    500 on at

    6327.Untitled.png

    Herewith i have attached screen prints of planning worksheet(PW) & SKU list for the items which are in PW.

    According to your explanation what may be the my error point ?

  • Verified answer
    Aleksandar Totovic Profile Picture
    16,765 on at

    My wrong:

    NAV2013/Make-to-Order: "Explodes the BOM and creates an additional production order or production order proposal line for each level in the BOM structure where that item's manufacturing policy has also been defined as make-to-order."

    NAV2009/Make-to-Order: "Explodes the BOM, and creates an additional production order line or production order proposal line for each level in the BOM structure where that item's manufacturing policy has also been defined as make-to-order."

  • Suggested answer
    Tanya Susan Profile Picture
    500 on at

    You mean both versions are same,

    If yes,

    is there are any parameter setting mistake of my scenario ?

  • Aleksandar Totovic Profile Picture
    16,765 on at

    Read carefully, there is little difference (yellow marked): order (2013) / order line (2009).

  • Suggested answer
    Tanya Susan Profile Picture
    500 on at

    Yes got it, thanks a lot .

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

#1
HoangNam Profile Picture

HoangNam 7

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans