Resource scheduling in D365 FO Projects

(0) ShareShare
ReportReport
Posted on by

Hi All,

Is it recommended to only do soft booking and soft assignment of resource to a project without doing hard book/ assign process. What would be the implication of keeping the process only at soft book and soft assgin stage ?

Regards,

Nakul

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    301,148 Super User 2025 Season 2 on at

    Moved the question to the Dynamics 365 Finance forum.

  • André Arnaud de Calavon Profile Picture
    301,148 Super User 2025 Season 2 on at

    Hi Nakul,

    You can only use soft planning or no planning at all. It doesn't matter for time writing. The only difference is the visibility in resource availability. When you don't do a hard planning, you don't know the difference between committed resources and reserved resources.

  • Suggested answer
    Miguel Angel Garcia  Profile Picture
    on at

    Hi Nakul,


    Be aware that Soft booking is a tentative reservation where the time of worker could still be reserved for other projects. By having a difference with Hard booking (firm reservation) where the time of worker cannot be reserved in other projects.


    There is an important workflow you can set up (Resource request workflow) where Project Managers can submit requests for the resources desired in the projects and the Resources Managers can approve/reject the requests. Project Managers submit the request of workers by soft booking in projects, whenever the Resource Manager approve the request, the tentative booking (soft booking) is automatically converted to Hard booking (firm reservation). You can take the advantage of this flow too (from Soft to Hard).


    Kind Regards

  • Community Member Profile Picture
    on at

    Thanks Miguel,

    I am just wondering that even if you do a hard assgin, still you can hard book/ hard assign the same resource on some other project and system will just highlight the resource with red color as overbooked but will never stop user from hard book/hard assign a resource already hard assigned to another project.

  • Suggested answer
    Miguel Angel Garcia  Profile Picture
    on at

    Hi Nakul, 

    When you made a hard assignment (firm booking) those hours cannot be booked to other projects. Based on the schedule calendar set up for worker (e.g. frequent 8 hour per day) you could hard assign 5 hours to a project, then there will be 3 hours left for same worker in the same day which could be still assigned to another project. However, if total hour per day for worker has been hard booked  (e.g. 8 Hours) you cannot book these to other project.

     Kind Regards

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 449 Super User 2025 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 422 Most Valuable Professional

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 239 Most Valuable Professional