Purchase Order Pre-encumbrance

(0) ShareShare
ReportReport
Posted on by 680

Hi All,

Having an issue where we have Pre-Encumbrance enabled for Purchase Requisitions.  When a user creates a PR and it goes through the workflow, it does a budget check etc.  Now when it comes to creating a Purchase Order with the PR.....we're receiving an error that the transaction exceeds the budget funds available.

When I go to budget control Statistics and look up the dimension used for the PR/PO.......I can clearly see that I have the funds available....with a pre-encumbrance amount.

Not sure if I'm explaining this right......but can someone point me in the right direction on how do I get around this as I'm new to AX.

Thanks 

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    syed baber Profile Picture
    11,633 on at

    Hi Nemesis,

    In addition to the financial dimension, have you looked at the Main account as well on Budget control statistics form and match with the main account used for PO transaction?

    Thanks,

    Baber.

  • Nemesis Profile Picture
    680 on at

    Hi Baber,

    I did look into this.....but no difference.

  • syed baber Profile Picture
    11,633 on at

    Hi Nemesis,

    On purchase order, accounting distribution form, ledger account is the same for which you have balance showing in budget control statistics?

    Thanks,

    Baber.

  • Nemesis Profile Picture
    680 on at

    Yes it is.  IDK whats going on.  And its only happening for this account.

  • syed baber Profile Picture
    11,633 on at

    Hi Nemesis,

    Can you please paste the screen shots of PO Accounting distribution form and budget control statistics form with the ledger account selected, so that I can better understand what is wrong here?

    Thanks,

    Baber.

  • Nemesis Profile Picture
    680 on at

    See the pre-encumbrance screenshot below. Follow by the encumbrance.  I assumed that this should have been updated to a 'Confirmed' status as with encumbrance. 

    PRE_2D00_Encumbrance1.png

    PRE_2D00_Encumbrance1.png

  • Khaled Alloud Profile Picture
    3,658 on at

    Hello,

    Please advice if the issue is still there, if it is solved please tell us how it is solved.

    You may check Budget control configuration. Have you seen the Budget funds available column?

    thank you,

  • Adineh Negahdari Profile Picture
    807 on at

    Is a Project ID Available on the PR?

  • Adineh Negahdari Profile Picture
    807 on at

    Is a Project ID Available on the PR?

    if yes update the Funding Limit amount on Project's Contract.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans