Does Project Operations use the universal scheduler for resource management?

(0) ShareShare
ReportReport
Posted on by 5

The microsoft docs say that PSA uses the universal scheduler but I could not tell if Project Operations does for resource management.

My requirement is fairly light-touch project planning with a heavy does of closely-managed hour-by-hour resource scheduling, and I want some of the Project Operations features (eg. activity cost management) but I don't want to lose the benefits of the Universal scheduler.

Anyone know?

thanks

I have the same question (0)
  • Verified answer
    apa Profile Picture
    8,284 Moderator on at

    Hi patrcikwillis.

    ProjOps uses Universal Resource Scheduling (URS). It's a platform horizontal and is used by PSA, ProjOps, FS, CS and Sales.

    For granular resource management it's worth mentioning that resource assignment contours are still locked for editing so matching assignments with bookings is currently a bit problematic. Assignment contour editing will be unblocked in the short term.

  • patrcikwillis Profile Picture
    5 on at

    Thanks Antii - really helpful.

  • patrcikwillis Profile Picture
    5 on at

    If you could elaborate.... I don't need complex contouring... I simply need something like:

    Task A - 09:00-13:00 4/4/21 - who is available with the right skills?  and then make soft/hard bookings

    I would just use Cust Svc or some custom tables, but I wanted the expense management and the project extensions to the Sales processes so I thought PrjOps lite, but not if the straightforward scenario above isn't seamlessly supported!

    Any extra input much appreciated.

  • apa Profile Picture
    8,284 Moderator on at

     patrcikwillis short answer is yeah, you can do that. The long answer is that it's a bit more complicated in ProjOps due to how resource management in ProjOps works: we book resources on projects but we assign them on tasks. I can give you a run-through of resource management in ProjOps if you want to jump on a call. Feel free to reach out to me at antti"at"anttipajunen.com.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 692

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 532 Super User 2026 Season 1

#3
CP04-islander Profile Picture

CP04-islander 478

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans