Item Charges on Purchase Receipt that is attributed to a Production PO

(5) ShareShare
ReportReport
Posted on by 231
We are trying to assign a PO Item Charge to 3 different Purchase Receipts.
 
2 of the Receipts cannot be assigned because they are attributed to a Production Order.
I cannot bring in those receipts into the Item Charges Lines in the PO
 
 
 
What are my options now to be able to assign the Item Charges to those Receipts?
I have the same question (0)
  • Suggested answer
    Suresh Kulla Profile Picture
    50,243 Super User 2025 Season 2 on at
    It is the restriction in the base product, you cannot assign item charges for subcontract POs, either you have make a customization to remove it but I am not sure how that will affect the costing and posting process, other alternative is discussed in the below link, please check
     
  • Verified answer
    BryLearnsBC Profile Picture
    231 on at
    I found the solution!
     
    The Purchase Receipt does not exist in ILE, but the Production document does!
     
    Use the "apply to Item Ledger Entry" function and look for the document number and it will allow you to add it to the "Assign item charges" page.
     
    Item Charge PO got posted and applied the cost to each item after the cost adjustment.
  • Suggested answer
    YUN ZHU Profile Picture
    95,329 Super User 2025 Season 2 on at
    Hi, Is this a custom environment? Purchase Receipts will definitely generate Item Ledger Entries.
    In any case, as long as you can find a solution.
     
    Thanks.
    ZHU
  • Suggested answer
    Sohail Ahmed Profile Picture
    11,136 Super User 2025 Season 2 on at
    In this case you can’t assign the charge directly to receipts linked to a Production Order. The workaround is to use “Apply to Item Ledger Entries” when posting the item charge. That way you can distribute the cost to the production-related entries instead of the receipts.
     
    ✅ Mark this as the verified answer if helpful.
     
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 3,143

#2
Jainam M. Kothari Profile Picture

Jainam M. Kothari 1,694 Super User 2025 Season 2

#3
YUN ZHU Profile Picture

YUN ZHU 1,067 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans