I have a question regarding replan function on the production order.
Example:-
Parent item - consists with two component items (Production BOM)
Component 1 conssits with two component items (Production BOM)
Assume taht there are inventory available for component 1.
I created a production order for parent item and refreshed the production order. Then I clicked on replan button on the production order.
System created a new production order for component 1 even though the sufficience inventory is available. Is this normal. The requirement is not to create production orders for lower level if the inventory is available. Do I need to make any changes to achieve that requirement?
Hello,
I think using this link you can solve the point.