Hi Guys
Does anyone know how can we Schedule Reschedule Production Order jobs as per assigned Priorities in the Priority fields?
Also Rescheduling the Production orders once jobs are in progress? (in case where Production orders are running but we have got some critical order to accomplish first)
Correct, the field priority does not have any D365 logic as far as I know , but it allows you to manage manually the sequence .
You can use the data entity batch order ( or work order ) to mass update the field and assign the priority (but orders will need to be in status created) unless you customize the data entity
Regarding your request
Also on the scenario where current production orders are running but i have to accommodate a new production order coming with very high priority?
you can reschedule manually that order
Hi Alessandro
Thanks for replying.
You mean i have to manually schedule based on Priorities. e.g I will schedule with higher priority ist and then schedule 2nd then 3rd?
How about Rescheduling? Also on the scenario where current production orders are running but i have to accommodate a new production order coming with very high priority?
I will definitely look into the sequencing feature if it can help in the scenario.
The priority button ( which was in AX 2009) has been removed as you can actually used an advanced filter and schedule by priority ascending and descending.
The priority field is very useful to sequence the batch or work orders and reschedule forward based on that sequence.
moved to the d365 forum
Hi Ludwig
Operating D365FO.
Please find below:
In route card, we use Job scheduling, which creates the jobs
Priority we mention/edit in the field below: On default it is "0"
Now the scenario is to Reschuling. If we allow the Rescheduling in Production Status in parameters only, then we can use the given screen:
Here we dont have any option for Priority based scheduling and the option in text is for Resource selection priority not the Production order priority.
So how can we do this? and also dont find any bigger purpose of Production order priority field.
Hi,
Do you operate D365FO or AX2012?
Irrespective of that, can you share details of your scheduling setup? Especially the resources and priorities that you have set up?
Some screenprints would be great.
Best regards,
Ludwig
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,240 Super User 2024 Season 2
Martin Dráb 230,149 Most Valuable Professional
nmaenpaa 101,156