Production Order Priority based Job Scheduling/Rescheduling

(0) ShareShare
ReportReport
Posted on by 139

Hi Guys

Does anyone know how can we Schedule Reschedule Production Order jobs as per assigned Priorities in the Priority fields?

Also Rescheduling the Production orders once jobs are in progress? (in case where Production orders are running but we have got some critical order to accomplish first)

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    Hi,

    Do you operate D365FO or AX2012?

    Irrespective of that, can you share details of your scheduling setup? Especially the resources and priorities that you have set up?

    Some screenprints would be great.

    Best regards,

    Ludwig

  • Mubeen Faizullah Profile Picture
    139 on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    Hi Ludwig

    Operating D365FO.

    Please find below:

    1460.pastedimage1630326335103v1.png

    In route card, we use Job scheduling, which creates the jobs

    8712.pastedimage1630326454342v2.png

    Priority we mention/edit in the field below: On default it is "0"

    8666.pastedimage1630326557911v3.png

    Now the scenario is to Reschuling. If we allow the Rescheduling in Production Status in parameters only, then we can use the given screen:

    7128.pastedimage1630326688225v4.png

    1541.pastedimage1630326763285v5.png

    Here we dont have any option for Priority based scheduling and the option in text is for Resource selection priority not the Production order priority.

    So how can we do this? and also dont find any bigger purpose of Production order priority field.

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    moved to the d365 forum

  • Aparisi82 Profile Picture
    2,180 on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    The priority button ( which was in AX 2009) has been removed as you can actually used an advanced filter and schedule by priority ascending and descending.

    The priority field is  very useful to sequence the batch or work orders and reschedule forward based on that sequence.

  • Mubeen Faizullah Profile Picture
    139 on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    Hi Alessandro

    Thanks for replying.

    You mean i have to manually schedule based on Priorities. e.g I will schedule with higher priority ist and then schedule 2nd then 3rd?

    How about Rescheduling? Also on the scenario where current production orders are running but i have to accommodate a new production order coming with very high priority?

    I will definitely look into the sequencing feature if it can help in the scenario.

  • Aparisi82 Profile Picture
    2,180 on at
    RE: Production Order Priority based Job Scheduling/Rescheduling

    Correct, the field priority does not have any D365 logic as far as I know , but it allows you to manage manually the sequence .

    You can use the data entity batch order ( or work order )  to mass update the field and assign the priority (but orders will need to be in status created) unless you customize the data entity

    Regarding your request

    Also on the scenario where current production orders are running but i have to accommodate a new production order coming with very high priority?

    you can reschedule manually that order

  • Suggested answer
    AD-15051158-0 Profile Picture
    on at
    Production Order Priority based Job Scheduling/Rescheduling
    Please have a look at job scheduling and parameters per order; then sorting. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
CA Neeraj Kumar Profile Picture

CA Neeraj Kumar 838

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 247 Super User 2025 Season 2

#3
Sagar Suman Profile Picture

Sagar Suman 235 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans