I am defining the cost price per Resource as below in the projects module:
1. Role Cost as 100
2. Resource Cost as 1250
3. Resource Cost per Role as 1000
CASE 1: When I select the Resource in the WBS, it does not pickup the cost price,
CASE 2: When I select the Role ID in the WBS, it picks up the cost price.
1522
I need the system to pickup the price for the CASE 1: Any Suggestions.