Master Planning - Why is MRP run to deducting twice for the inventory hold in net requirements?

(5) ShareShare
ReportReport
Posted on by 175
Hi All,
I have an item which has around 3279 LBS blocked for consumption, which puts my available physical to 30350 lbs as seen below
 
When I run my MRP, I see the transaction again deducted from the available physical - need explanation on why its double dipping:  Why is system deducting the available physical to Push the accumulated QTY to go -ve.
 
  • Guy Terry Profile Picture
    29,024 Moderator on at
    The problem there is that your On-hand line in Net requirements is not showing the true Physical Inventory. That line should say 6330.78. Have you run MRP or updated Net requirements for that item recently?
  • Suggested answer
    Laurens vd Tang Profile Picture
    5,047 Super User 2026 Season 2 on at
    Good day,

    I've encountered the same issue as well. In my case, there was an open journal (adjustment, movement, or counting).

    Could you check if there is an open journal?

     
    It looks like the MRP is seeing the journal as a potential negative stock adjustment.
     
    Best regards,
    Laurens van der Tang
     
     
  • AH-07052021-0 Profile Picture
    175 on at
    This is after I ran the master planning and I ran the master plan today, that's where I got confused as why - On hand Inventory showing -Available Physical than Physical inventory.
  • Guy Terry Profile Picture
    29,024 Moderator on at
    On the Net requirements screen, at the top, do Update > Master planning. Make a note of the name of the Master Plan that will be updated (and select your Dynamic plan if you want). Then hit OK.
     
    This will regenerate the data for this item (in the Plan you selected). Make sure Net requirements is showing the Plan you just updated, then check the numbers again.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the July Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 99 Super User 2026 Season 2

#2
Paolo Cecchelli Profile Picture

Paolo Cecchelli 79 Super User 2026 Season 2

#3
Aayush Tiwari Profile Picture

Aayush Tiwari 71

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans