standard cost change

(0) ShareShare
ReportReport
Posted on by

I have changed standard cost (old sc=10, new sc=12), when update standard cost, new calculation using new standard cost (12).

but when I changed standtard cost (old sc=10, new sc=10500), new calculation still using olde standard cost (10).

please give me help

thak's

*This post is locked for comments

I have the same question (0)
  • Blue Wang Profile Picture
    Microsoft Employee on at

    Hi Fajar_IT,

    Have you set the range of values?

    10500 is out of range, causes new values to be invalid

    You can change to a smaller value, such as 5000, and to see if it works.

    Best Regards,

    Blue Wang

  • Community Member Profile Picture
    on at

    Actually we use Indonesian Rupiah, set of value until trillion

  • Blue Wang Profile Picture
    Microsoft Employee on at

    Hi Fajar,

    Did you forget to change the type of currency?

    Can you provide more information about the way to change your values?
    Thanks.

    Best Regards,
    Blue Wang

  • Suggested answer
    I Gusti Made Ari Profile Picture
    3,608 on at

    Hi Fajar,

    Does the item still have stock before you change the standard cost ?

    if yes, you will need to revaluate what you current have on hand to the new standard cost. Just updating the standard cost on the item card will only affect purchase or incoming items going forward.

    Below is guide line from microsoft :

    docs.microsoft.com/.../finance-how-to-update-standard-costs

  • Community Member Profile Picture
    on at

    Hi Made

    rest of stock already revaluate

  • I Gusti Made Ari Profile Picture
    3,608 on at

    if you have already completed the revaluation for current stock , it should be using the new standard cost. What  scenario that you did that you are still getting this "new calculation still using old standard cost (10)" ?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans