Hi
If the SO is from a xyz customer or if the SO is from a inter company then i don't want to run a master planing .
Is there any way to customize the master planing class to achieve this.
Thank you
*This post is locked for comments
Hi
If the SO is from a xyz customer or if the SO is from a inter company then i don't want to run a master planing .
Is there any way to customize the master planing class to achieve this.
Thank you
*This post is locked for comments
hi
thank for your reply
can you explain 1. Change req Group of item involved to coverage rule manually (depends on how many Different items are involved) where and how to set it as i am a technical guy less idea on functional side
The main reason is this SO is from inter company and the master planing for this item is already done in company A so in company B its not required to run master planning for this item
Hi Peter,
i would not recommend to customize planing as it works fine
on my opinion you have 2 possibilites to solve this case
1. Change req Group of item involved to coverage rule manually (depends on how many Different items are involved)
2. Change sales order type to Journal of xyz and ic so, so they would not run into planing.
But i do not understand the reason why you do not want plan some customers.
best regards
Albrecht