Purchase Requisition Vendor automatically filled in

(0) ShareShare
ReportReport
Posted on by 100
Good morning,
I have a problem when I create a purchase requisition if there is a purchase agreement the system automatically fills the supplier code. Is there a way to avoid this?
What I would like is that there is no supplier in the purchase request
Thank you
pastedimage1594279112220v2.png
I have the same question (0)
  • qianwang Profile Picture
    7,168 on at

    Hi Wilson78,

    Do you need to apply this agreement?

    If you don't need it, you can just delete the vendor. Then the purchase agreement status will be on hold.

  • MATTGUO Profile Picture
    22,349 Moderator on at

    Hi Wilson,

    There is no parameter that controls interaction of Purchase requisition lines and Purchase Agreements.

    Please consider customizing or creating an idea: experience.dynamics.com/.../

    And please have a look at this blog about the vendor of PR: https://msdynamicsworld.com/story/ax-7/purchase-requisition-and-vendor-selection-microsoft-dynamics-365-operations-and-ax-2012-t

  • Suggested answer
    saurabh bharti Profile Picture
    15,039 Moderator on at

    Hi Wilson,

    There is an option where in procurement and sourcing parameters > Find purchase agreement is setup which allow system to find agreement prices for PR/PO Lines.

    You can always remove vendor while releasing the PR for PO.

  • Wilson978 Profile Picture
    100 on at

    Hi saurabh bharti

    where i can find this option, i checked but i can't find it. It work both for PO and PR, i need only for PR.

    Thanks!!!

  • Suggested answer
    Rahul Mohta Profile Picture
    21,032 on at

    might need to customize and then create a control for PR only

  • Suggested answer
    saurabh bharti Profile Picture
    15,039 Moderator on at

    Hi Wilson,

    Navigate to : Procurement and sourcing > setup > Parameters > Prices > Remove Purchase requisition from evaluation, so it should not consider trade agreement for PR

    pastedimage1594539932729v1.png

  • Wilson978 Profile Picture
    100 on at

    Thank you for your answer, but doesn't work!

  • Suggested answer
    Rahul Mohta Profile Picture
    21,032 on at

    is there any customization in your PR?

    not seeing PR and PA link

  • Suggested answer
    saurabh bharti Profile Picture
    15,039 Moderator on at

    Then i think you have to go for some customization for the same.

  • Suggested answer
    Vamsi Pranith Profile Picture
    682 on at

    Are you using an item along with the procurement category? If so, it takes from the release product setup of default vendor. I would start looking there before researching if there is any custom code.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 299 Super User 2025 Season 2

#2
Siv Sagar Profile Picture

Siv Sagar 183 Super User 2025 Season 2

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 118 Super User 2025 Season 2

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans