Suggested Answer

Planned orders not considering on hand stock

(0) ShareShare
ReportReport
Posted on by 75

When runing Master scheduling in AX 2012 R3, the planned orders are not considering the on hand stock, even the setting is activated in master plan. Please advise

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    306,859 Super User 2026 Season 2 on at

    Hi Dalila,

    The master planning has a lot of settings which can influence this behavior. Can you provide what exact settings you have in the parameters, master planning and coverage groups?

  • dalila Profile Picture
    75 on at

    Hello André, Thank you for your response, my setting is as below :

    My master Plan :

    6545.pastedimage1621766080370v1.png

    0624.pastedimage1621766129021v2.png

    Coverage Group : 

    7888.pastedimage1621766185163v3.png

    With entry of supply forecast/warehouse, then master scheduling calculation, the result is production planned orders for qty = supply forecast qty (and respective raw materials on panned purchase orders), even the finished good is existing in stock within good shelf life dates. 

    Thanks a lot in advance for your support. 

  • André Arnaud de Calavon Profile Picture
    306,859 Super User 2026 Season 2 on at

    Hi Dalila,

    Can you also provide information about the current active inventory transactions + on-hand and the forecast? On the planned production order, what is the information related to the 'Pegging details'?

  • dalila Profile Picture
    75 on at

    Dear André,

    Thanks a lot for your answer, and please to find my example :

    On hand stock of item SS017P01 : 170 445 (nettable and not expired)

    pastedimage1621870804133v1.png

    The supply forecast : with selection of activated formula 

    pastedimage1621871123484v2.png

    When performing the above sypply schedule, planned orders are : 

    Qty in plan is exactly the forecast one, no consideration of stock 

    pastedimage1621871467301v3.png

    and pegging section in the prod planned order is empty : 

    pastedimage1621871546497v4.png

    Appreciate your kind support, thanks in advance André.

    Best regards. 

  • Suggested answer
    André Arnaud de Calavon Profile Picture
    306,859 Super User 2026 Season 2 on at

    The on-hand and forecast are not linked. The reduction principle on the master plan settings is set to none, so it will take all quantity into account. You can learn more about forecast reduction in the documentation and Lachlan created a video with explanaition:

    Forecast reduction keys - Supply Chain Management | Dynamics 365 | Microsoft Docs

    Reduction of forecast in master planning. | OrganicAX

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the July Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 92 Super User 2026 Season 2

#2
Laurens vd Tang Profile Picture

Laurens vd Tang 66 Super User 2026 Season 2

#2
Paolo Cecchelli Profile Picture

Paolo Cecchelli 66 Super User 2026 Season 2

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans