Account number for transaction type Project - cost does not exist. But it should

(1) ShareShare
ReportReport
Posted on by 1,004

Today I began working in our test environment but I cannot post in the project module.  All postings are set up in Project management>Setup>Ledger posting setup.  The account structure looks valid as well in General ledger>setup>Ledger.  Everything works outside of projects.  Has anyone ever come across this?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Richard,

    If you have setup all necessary accounts in the ledger posting form then this issue might be related to a bug. On LCS I have found hotfixed that refer to the project posting type project - WIP but not to the project posting type cost. If you have not made any customizations and do not have a developer on hand to debug, I would suggest that you contact the MS Support directly. They might be able to help you hopefully quickly.

    Best regards,

    Ludwig

  • Anisha Fakir Profile Picture
    680 on at

    Hi Richard,

    Check your account structure.

    Ensure your project ledger accounts are included in the range specified in the account structures.

  • Richard Wehmeyer Profile Picture
    1,004 on at

    Account structure seems legit and it is not just Project - cost it is EVERY project posting.

    6_2D00_24_2D00_2016-10_2D00_21_2D00_45-AM.jpg

    6_2D00_24_2D00_2016-10_2D00_21_2D00_45-AM.jpg

    6_2D00_24_2D00_2016-10_2D00_22_2D00_21-AM.jpg

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Richard,

    Can you test whether setting up the cost account 610109 under GL/Setup/Posting/Accounts for automatic Transactions for the posting type "Project - cost" helps?

    Ludwig

  • Richard Wehmeyer Profile Picture
    1,004 on at

    Added the account, deleted item journal line, created new line, posted journal

    6_2D00_24_2D00_2016-10_2D00_38_2D00_37-AM.jpg

    No change

    By the way: this is a copy of our Live environment we have been testing in since September.  The last time it worked was late May so something has changed recently.

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Richard,

    If it worked before then I could imagine that the issue is caused by a modification implemented. I would suggest that you ask one of your developers to take a look at what changed since September. Maybe they just forgot compiling/syncronizing something?!

    Would be great if you could keep us updated.

    Many thanks,

    Ludwig

  • David Massey Profile Picture
    on at

    Can you specify with business document you are attempting to post?  Since Payroll allocation is being displayed with an error above, I'm assuming it is relate to posting Hours. There are multiple documents/processes which can post hour transactions.

  • Anisha Fakir Profile Picture
    680 on at

    Hi Richard,

    Usually when this error appears in the AP or AR modules it is related to the posting profile group the customer/vendor is assigned too is different to what is stated on the PO/SO.

    So have a look at your project, ensure your categories or project group on which your postings are setup is setup correctly and there are no data issues.

    As Ludwig mentioned, get a technical person to debug the process, they will easily spot where the actual problem lies.

    Regards,

    Anisha

  • Verified answer
    Richard Wehmeyer Profile Picture
    1,004 on at

    Found it:

    I tried doing a movement journal on one of the accounts in IWM and it failed similarly so it is on the accounts and not a project issue.

    I compared the ledger and found the accounts separated by a comma.  changed this to a ";" and reaactivated and it works!  

    8206.6_2D00_24_2D00_2016-10_2D00_22_2D00_21-AM.jpg

    Not sure if it was the syntax or the reactivation.  Thanks for the help

  • Community Member Profile Picture
    on at

    I am also facing same issue. I also checked all nodes, which are using ; so its means that nodes are entered correct. what else i can do to resolve same issue. i am also confused.

    i also modify the form. but for some projects, main account and sub account fields are working good but for some project i got same error. so what i can do?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans