How to Reopened PR when the PO line is already deleted

(0) ShareShare
ReportReport
Posted on by

HI Expert,

We have an issue, when our Purchasing agent suddenly delete one line from Po that coming from PR. We cancelled all The PO, but the PR still closed not change to approved.

Therefore, we can't released the PR to Approved. If we checked on the PR, the PO number still there. the question is how to break the link from PO that already deleted and the second is how to reopened again the PR

Regards

RIdwan Tahir

*This post is locked for comments

I have the same question (0)
  • NaveenKumar S Profile Picture
    3,477 on at

    Hello, 

    As long as the PO is not confirmed you can delete the PO line or PO and the PR will change the status to approved from closed. But once PO is confirmed, the PR and PO will be linked. so now if one removes the line from PO and confirm the PO again, PR will not get disassociated with PO line, this is to track the PO. It is std. system functionality. As a work around you need to cancel the PO and Create a new PR and convert the PO.

  • Community Member Profile Picture
    on at

    HI Naveen, 

    Thanks for the replied. We have tried to remove the line when the PO is closed. However the PR still closed instead of Approved. Is there any particular configuration that we should do?

  • NaveenKumar S Profile Picture
    3,477 on at

    Hello Ridwan,

    There is no configuration for changing the status for PR. Since you are able to process the PR cycle i can assume your configurations are correct. I suggest you to create a new PR and continue. As for this PR, since the related PO is cancelled, there should not be any issues

  • Community Member Profile Picture
    on at

    hi Naveen,

    For this PR, we created the new one. However, we just think for the next. if the process is happening again? In my opinion, its the normal standard when the PO cancelled the PR is Open  

    Regards

    Ridwan Tahir

  • Suggested answer
    NaveenKumar S Profile Picture
    3,477 on at

    Hello Ridwan,

    I agree with you, if we look at business process, your points is valid.

    In ax we do get the option to do this as long as PO is not confirmed, we get the below message when we try to delete the PO

    1464.1.jpg

    but after PO confirmation we dont have this option, however PO confirmation versions will maintain the record of these changes. 

  • Community Member Profile Picture
    on at

    Hi Naveen,

    Really appreciate for your reply.However, on our system there is no message when we remove the line even when The PO status is approved.Thats why, i'm curious whether we have some missing in configuration or not.

    Ridwan

  • NaveenKumar S Profile Picture
    3,477 on at

    Hello Ridwan,

    is it possible to share your screen so that we can debug

  • Community Member Profile Picture
    on at

    Hi Naveen,

    Unfortunately, our policy not allowed us to do that. Could you guide me, what we should check? we will screen shot it 

    Regards

    Ridwan Tahir

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#2
Henrik Nordlöf Profile Picture

Henrik Nordlöf 2 User Group Leader

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans