Hi
i have demande thé is loaded into dynamics for a semi finished product and a finished product.
the SF product is consumed into the finished product.
problem, when MRP runs it calculates the requirements twice. Once for the finished good line items, where it calculates the SF requirement but also creates the raw material requirement for the SM product.
secondly, this is again (correctly) created for the semi finished product. This suggesting double the amount of raw material needed.
hoping someone can help!
thanks