Resource scheduling issue

(0) ShareShare
ReportReport
Posted on by

Hello everyone, 

We created a project with a defined start date and were able to add resource to the project. 

However, when we go to Specify resource hours, the start and end date are incorrect ( start and end date are in 1900) and the resource can't be booked. 

I have to mention that this is not happening with every project, only certain ones and we can't figure out why is it happening.

Screenshots attached.

pastedimage1628602044027v1.png

pastedimage1628602080912v2.png

Regards, 

Teodora

I have the same question (0)
  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Teodora,

    Does Dynamics not allow you to change that start and end dates?

    What exactly is the issue here?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    Hi Ludwig,

    The issue is not that I can't change the start/end date on the project or the scheduling form.

    The issue is that even when I do that, on specify resource hours form start date is empty and end date is set to 02/01/1900 00:59.

    Regards,

    Teodora

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Teodora,

    I see.

    Do you know if some of your colleagues made some modifications to the standard resource scheduling functionality?

    Is that a MS demo / dev company with Contoso data or a customer engine?

    Best regards,

    Ludwig

  • Community Member Profile Picture
    on at

    Hi Ludwig,

    This is a customer engine.

    We have made some modification to the standard functionality, yes.

    However, this is not happening in all Legal entities and projects, that is why we don't believe it's due to the modifications we have made in the system.

    Regards,

    Teodora

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 660 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 549 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 307 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans