Realization of consumed hours and consumed cost amount on Secondary 1 operations

(0) ShareShare
ReportReport
Posted on by

Hi,

We have introduced Secondary 1 Priorities (together with Primary Priority) on same Operation number for our production routes. This in order to split our Operations by different Man- and Machine-related cost categories (with differentiated hourly cost rates). Number of estimated hours for the Primary and Secondary 1 Operations are always the same.

However, in price calculation when comparing the estimated consumption of hours and cost amounts for those hours on line level and total level we don't get any realized consumption and cost amount for hours reported on Secondary 1 Operations.

We are running AX 2012 R2 CU6, Kernel version 6.0.1000.2473. 

Which further actions must I take to prepare AX to realize consumption of hours and cost amounts for the Secondary 1 Operations ?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Fredrik Sætre Profile Picture
    12,644 on at

    Try me deling with the Secondary 1 route group... Can you post a screenshot from the one you are using?

  • Suggested answer
    Community Member Profile Picture
    on at

    Hej Fredrik,

    I am applying route group STD with same setup for both Primary and Secondary 1 route operations. Print screen of applied setup is attached.

    Do I need to have an additional route group with different setup for the Secondary 1 route operations ?

    Best regards,

    Göran Håkansson

    5482.setup.PNG

  • Fredrik Sætre Profile Picture
    12,644 on at

    Try adding another group and tick for automatic consumption.

  • Community Member Profile Picture
    on at

    We have tried this, but any automatic consumption doesn't take place. We are forced to manually consume both Primary and Secondary 1 Operations in order to achieve estimated and realized consumption of hours. We have even tried tick-marking automatic consumption for the "old" route group, which is linked to the Primary Operations, but we are still forced to consume/report manually.

    What is the root cause for this behaviour ?

    Best regards,

    Göran Håkansson

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans