I detect a strange behavior in the field : msdyn_todate in the entity msdyn_resourcerequirement.
The behavior is the follow:
When I create a new requirement for a work order and indicate the dates, msdyn_fromdate and msdyn_todate. The system allways adds 24 hours to msdyn_todate and I don't know why.
I review the field service setting and I don't find where this time is configurating, I think that this behavior is for a pluggin.
Thanks,
I think we had a very similar issue. We were creating the Resource Requirements by a custom plugin and somehow the system added 2, sometimes even 3 more days automatically to those fields. We couldn't find out why. I think our developer simply overwrote the final values again which was not how it normally should work.
So most probably it is a Microsoft bug here. Hope they fix it, if not already happened.
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,253 Super User 2024 Season 2
Martin Dráb 230,188 Most Valuable Professional
nmaenpaa 101,156