Hello all, I'm trying to utilize the Project module and the primary objective I have with it right now is to relate Materials Purchases to specific projects. When I try to add an inventory item to a PO that is associated with a Project and Cost Category, I get a message that says "The Price Level/U of M combination is not setup for this item in the Price List" or something to that effect. The problem is that the Price List is completely setup for the item. One other data point - the Project Module did seem to force me to turn Multi-Currency on. It was the only way I could add a Project. The price list does not have a Currency ID setup. I am thinking that may be a problem, but when I try to go to the Item Currency card under Inventory I get the following: "The Item Currency Maintenance window is available only when Multicurrency is registered."
Anyone have any ideas on what is going on here?
Thanks,
Scott
*This post is locked for comments