Hi All,
 
I am having a problem with trying to utilise the MPS function of Business central to replicate my production environment.
 
We have 25+ work/machine centres for assembly and manufacturing routings that all require an operator to run each station. The issue is that we have 10 operators, for example, so we would be unable to run all work/machine centres at the same so would need the MPS to account for blocking out 15 work/machine centres while the other 10 are occupied, is this possible to implement within Business Central?
 
Thanks for your help!
 
Matt
I have the same question (0)
  • Verified answer
    Ben Baxter Profile Picture
    7,107 Super User 2026 Season 1 on at
    Matt,
     
    Your Routing would need to be Type = Parallel, and include an Operation for the Machine and an Operation for the Machine Operator.  You can adjust the Next/Previous Operation values to assign which Operations run concurrently (Machine + Operator).  Sequence of Operation is important if the Operator is only required for Setup, rather than full concurrent requirements.
     
    This will get you much closer to your goal, but you still may want to look at some of the scheduling solutions available from Insight Works or Netronics to see if their solution would be beneficial to your operation.
     
    P.S. If this reply helped you, please mark it as a Verified Answer.  This helps other forum users find it quickly.
     
    Best Regards,
    Ben Baxter
    Accent Software Inc
  • MB-27040939-0 Profile Picture
    4 on at
    Brilliant, thank you Ben. I have managed to get the Planning worksheet to behave much closer to what we need. We are in the process of implementing Netronics VAPS, using this method schedules correctly under the Operator work centre but still tries to schedule the actual work centres as if they were independent.
    Thanks again for you help!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Launch!

Jump in, show your community spirit, and win prizes!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,497 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,778 Super User 2026 Season 1

#3
AndrewThomas81 Profile Picture

AndrewThomas81 1,507

Last 30 days Overall leaderboard

Featured topics

Microsoft Training Manuals

Product updates

Dynamics 365 release plans