Budjet import

Posted on by 1,465

Hi!

I have to re upload  revised budget second  time this year. Curious may it cause duplications somehow? I'm doing it in automated transaction import by using Budget Maintenance screen.

*This post is locked for comments

  • Erich Strelow F Profile Picture
    Erich Strelow F 1,642 on at
    RE: Budjet import

    For every new revision you should check if "Rev Type" is either "New Amounts" or "Net Change".

    "Net Change" indeed does add/substract the new budget amount to the one already loaded inside the project. "New Amounts" replaces the whole value.

    If you intend to do a "News Amounts" but have the "Net Change" selected, the effect will indeed be that the values get duplicated.

  • Verified answer
    Ajit Kannan Profile Picture
    Ajit Kannan 1,240 on at
    RE: Budjet import

    Hi ANDREW

    You can better calculate the sum of Budget amt based on accct,subacct,ledgerid & year.

    And import the data through TI Process.

    Hope this will help,

    Thanks,

  • Coen Pretorius Profile Picture
    Coen Pretorius 890 on at
    RE: Budjet import

    Just to clarify.

    Whatever you import will become the new budget for the combinations of accct,subacct,ledgerid and year that you import. Whichever combinations exist in the current budget , and which are not included in the import, will remain and become part of the "revised" budget

  • Coen Pretorius Profile Picture
    Coen Pretorius 890 on at
    RE: Budjet import

    My Apologies, I assumed you were talking about project budgets.

    Everytime you import a budget for the same acct, subacct, ledgerid and year, it overwrites the existing budget.

    So whatever you import will become the new budget.

  • Andrew73 Profile Picture
    Andrew73 1,465 on at
    RE: Budjet import

    Hi Coen,

    I'm using Budget Maintenance(01.250.00).

    Thanks!

  • Coen Pretorius Profile Picture
    Coen Pretorius 890 on at
    RE: Budjet import

    Are you using the Budget REVISION maintenance screen in other words the project is set up on Project Maintenance Screen for "Budget By Revisions" or are you using Direct Budgeting Option?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,214 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans