Hi!

I have to re upload  revised budget second  time this year. Curious may it cause duplications somehow? I'm doing it in automated transaction import by using Budget Maintenance screen.

*This post is locked for comments

I have the same question (0)
  • Coen Pretorius Profile Picture
    904 on at
    RE: Budjet import

    Are you using the Budget REVISION maintenance screen in other words the project is set up on Project Maintenance Screen for "Budget By Revisions" or are you using Direct Budgeting Option?

  • Andrew73 Profile Picture
    1,471 on at
    RE: Budjet import

    Hi Coen,

    I'm using Budget Maintenance(01.250.00).

    Thanks!

  • Coen Pretorius Profile Picture
    904 on at
    RE: Budjet import

    My Apologies, I assumed you were talking about project budgets.

    Everytime you import a budget for the same acct, subacct, ledgerid and year, it overwrites the existing budget.

    So whatever you import will become the new budget.

  • Coen Pretorius Profile Picture
    904 on at
    RE: Budjet import

    Just to clarify.

    Whatever you import will become the new budget for the combinations of accct,subacct,ledgerid and year that you import. Whichever combinations exist in the current budget , and which are not included in the import, will remain and become part of the "revised" budget

  • Verified answer
    Ajit Kannan Profile Picture
    1,246 on at
    RE: Budjet import

    Hi ANDREW

    You can better calculate the sum of Budget amt based on accct,subacct,ledgerid & year.

    And import the data through TI Process.

    Hope this will help,

    Thanks,

  • Erich Strelow F Profile Picture
    16 on at
    RE: Budjet import

    For every new revision you should check if "Rev Type" is either "New Amounts" or "Net Change".

    "Net Change" indeed does add/substract the new budget amount to the one already loaded inside the project. "New Amounts" replaces the whole value.

    If you intend to do a "News Amounts" but have the "Net Change" selected, the effect will indeed be that the values get duplicated.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics SL (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans