Hi,
I hope some one can help me quickly as on Monday I am supposed to give a training on PSA,...
I've created a trial instance and loaded the new demo data (Fabricam)
These are the steps I take and the issue I run into
- Navigate to Project Service | Projects
- Click the New Project button in the command bar
- Fill out following details:
- Name: < Standard Pilot Project>
- Customer: <Alpine Ski house>
- Save
- Open the Work Breakdown Structure of this project from the related entities
- The first task will be ‘Intake’ that will take 40hours.
- Click Add Task
- Task name: <Intake>
- Effort Hours:<40>
- On the task line, click the Assigned Resources column
- Then I get the error message: 'Create Project Task: an error has occurred while creating a task. The page will refresh to the last good state of the WBS(
- Then when clicking 'error details': 'The estimate header is missing'
So I'm unable to create any WBS,...
Thanks a million!