HI All,
I am looking for some help please. I work in a production plant that uses D365 and we're having a bit of an issue with Master Planning. When I checked planned purchase orders, I am getting lines through for raw materials that I have already ordered. When I look closer at the requirement profile, I then notice that we're getting planned works orders through for batches that are already firmed up, some with a due date of 17th December.
Does this sound familiar to anybody? Unfortunately because this is happening, MP isn't accurate.
Any help/advice is greatly appreciated!
Thanks
Lanna