Hello,
I'm new to AX so my question might be newbie.
The question is: When I run the Master Plan it gives me
Planned Production Order / Planned Transfer
When I firm the Planned Production Order then re-run the plan it gives no Planned Production Order which is totally correct.
The problem occur with the planned transfer so when I firm it what ever I left it a transfer or made a PO of it then re-run the plan it gives me a new Planned Transfer again wich is wrong and duplication.
So which setup part should I look into?