Hi All
When trying to assign a routing link code to anything other than line type = BOM on BOM lines we get an error. What is the reason for this setting?
Hi ,
Routing Link Codes are used to make an association between a routing operation step and the BOM components that will be used in the operation
it is basically use to make the relationship between the routing and the components used in that operation step.
Regards,
Alok Kulshreshtha
Please verify if you find my answer helpful
In your scenario you need to go to the phantom's BOM and set the Routing Link Code there. That way when the components are exploded on the Production Order they pass the Routing Link Code to the lines.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
OussamaSabbouh 677 Super User 2026 Season 1
Gerardo RenterÃa Ga... 447 Most Valuable Professional
YUN ZHU 366 Super User 2026 Season 1